In late June of 2006, the Chattahoochee River NRA began a year long river access construction project to improve the boat ramps.
The nature of this project has a high level of complexity, due to fluctuation with weather and the river flow and velocity. Therefore, the schedule may change during the course of construction.
The projected schedule below represents the park staff’s best efforts to anticipate the course and sequence of this project. This listing will be continuously updated as necessary and with as much advance notice as possible.
For information on the Paces Mill ramp closingclick here.
Current as of June 18, 2007
Location
Construction Dates
Palisades Sandy Point Steps
Construction Completed
Whitewater Creek Step Down Ramp
Construction Completed
Settles Bridge Step Down Ramp
Construction Completed
Jones Bridge Boat Ramp
Construction Completed
Johnson Ferry Boat Ramp
Construction Completed
Abbotts Bridge Boat Ramp
Construction Completed
Paces Mill Boat Ramp
Construction Completed